Friday, February 15, 2008
In an order issued Friday, the state body that regulates power lines approved the overhead construction of a 12-mile power line sought by Dominion Virginia Power.
The 230-kilovolt transmission line will run between the Pleasant View substation and a proposed Hamilton substation, the State Corporation Commission said.
The commission said the new transmission line should follow the "Modified D" route, which was recommended by an SCC hearing examiner. That 12-mile path runs through southern Leesburg and along parts of the Washington and Old Dominion Trail.
Final Order
Related Stories
Related Links
Advertisement
An SCC hearing examiner, Howard P. Anderson Jr., argued in November that the line should be carried overhead, in part via steel towers that would be more than 140 feet tall, because burying parts of it would be significantly more expensive and would uproot vegetation.
Opponents of putting the line above ground say it would be an eyesore and lower property values.
In Friday's order, the commission said, "No route can eliminate all adverse impacts." The order goes on to say the route minimizes "adverse impact on scenic assets, historic districts, and environments of areas concerned, and results in fewer adverse impacts than other proposed routes."
The SCC has found that the new transmission line is needed to serve the growing electricity demands in western Loudoun. The SCC said the line will be built on single-shaft poles "placed as far away from residences as possible."
The poles will be located on existing right-of-way owned by Dominion and the Virginia Department of Transportation wherever possible, according to the SCC.
The line is expected to be functioning by Jan. 1, 2011.
Tagged: Dominion , growth, power line
Maid To Please is offering LoudounExtra.com readers $25 off their first house cleaning, or $10 their third house cleaning.
• View all deals from Maid To Please | All deals
• $25 Off House Cleaning From Maid To Please! posted: 4/28/09
|
Search Deals and Business Directory |
Are you happy that the school year is over?
Comments:
Note: LoudounExtra.com does not necessarily agree with comments posted below — responsibility lies with the relevant reader alone. Peruse our reader agreement and privacy policy
What is Dominion going to do when the bridge is built OVER the bypass at Sycolin Rd in Leesburg, or when VDOT starts widening that stretch of road? Is Dominion even talking to VDOT or Leesburg on future road changes?
Posted by GenuineRisk (anonymous) on February 15, 2008 at 4:13 p.m. (Suggest removal)
why can't i find a map of the modified D route?
Are they trying to keep it a secret?
Posted by gillwald (anonymous) on February 18, 2008 at 11:34 a.m. (Suggest removal)
There's a map of the route here: http://www.dom.com/about/elec-transmissi...
Posted by Paradox13VA (anonymous) on February 19, 2008 at 11:30 a.m. (Suggest removal)
Dont have an account? Sign up!
Post a comment